Wednesday, January 14, 2004

STS-97 (Endeavour)

 2000-078A


The STS-97 flight took the P6 truss to the International Space Station. The P6 truss was easily latched to Z1 as EVA astronauts Tanner and Noriega guided it in, but during deploy of the solar arrays, a software problem delayed the effort. Solar wing 2B (the starboard wing) and 4B (the port wing) were to be deployed. 2B was deployed and tensioning wires came loose, so the port wing deploy was delayed and done slowly the next day.

On the second EVA P6 was wired up to the station. It was decided to add a new task to EVA-3: repairing 2B's tensioning wires. This was done quickly, and the original taks of installing the Floating Potential Probe experiment was done. This measures whether the PCU's are successful in bleeding off excess charge from the arrays; there was some fear that EVA astronauts might be hit by a bolt of lightning from the arrays. The FPPE was installed on top of P6 between the SAWs. The thermal cover of the FPPE has an evergreen drawn on it as a nod to the tradition of topping out a tall terrestrial construction project.

STS-97 uses RMS 303. Launch mass 120740 kg; landing mass 89756 kg. Mass at MECO 116264 kg, after OMS-2 114777 kg. A new GPS SIGI DTO experiment was carried. 641 kg of internal transfer, possibly including the 40 kg FPPE (of which 23 kg was the actual removable experiment).


STS-97 
 

DateTimeEventOrbit  

2000 Oct  Tow to VAB/1 
2000 Oct 27  Mate to ET 
2000 Oct 31   Roll to LC39B 
2000 Dec 1  0306:01 Launch  KSC LC39B 
 0308:04  SRB sep 
 0308:15  OMS assist 
 0309:57  OMS assist C/O 
 0314:27  MECO  74 x 325 km 
 0314:46  ET sep 
 0349:15 T+0:44 OMS-2 1:18 36m/s 
 0350:34 OMS-2 CO  205 x 322 km x 51.6 
 0430?  ET-105 reentry 
 0436:38 PLBD open 
 0649:17  OMS 3(R) 10.6s 3m/s 
 0704   89.79 205 x 322 x 51.6 
 1842:39  RCS NPC +X 20s 1.2m/s 
2000 Dec 1  2021 RMS checkout 
 2130  RMS cradle 
2000 Dec 2  0323:45  OMS 4 NC3 52s 24m/s 
 0324:37  OMS 4 CO 
 0600  90.66 238 x 374 x 51.6 

1600:09 OMS 5 burn 1:20 dv=38m/s 
 1635:01  NCC 4s 0.3m/s 
 1732:44  OMS 6(L) TI burn, range 15 km 2m/s 8s 
 1732:52  OMS 6 CO 
 1752:43 MC1 
 1754  Station orient, PMA-3 to nadir 
 1812:52  RCS planar null 
 1829:36  MC2 
 1846:36  MC3 
 1856:36  MC4 7s 
 1859 Manual control 2 km 
 1908  On R-bar 
 1913  150m range 
 1917  Rotate to align 
 1922  100m range 
 1924  85m range 
 1927  70m 
 1952  Resume approach at 30m 
 1959:40  Docking PMA-3  92.09 374 x 379 x 51.6 
 2011:51  Hard dock 
  RMS uncradle 
 2216:57  RMS grapple P6 
 2227  P6 unlatched 
 2229  P6 unberthed 

2252 HO to PMA-3 
 2320  P6 in park position 
2000 Dec 3 0022  Ingress to PMA-3 
 0140  HC to PMA-3 
 1545  P6 moving toward Z1 
 1614  P6 in premate position 1m from Z1 
 1820 Begin depress 
 1823 5psi, begin leak check 
 1825 Resume depress 
 1831 EVA-1 Tanner, Noriega 
 1830:47 Depress complete 
 1831 EAL HO  92.07 374 x 378 x 51.6 
 1835 Battery power 
 1840  Egress Tanner 
 1845? Egress Noriega 
 1920  EVA crew observe P6 mating 
 1932  P6 berthed on Z1 
 1940? P6 manually latched 
 2017:25  RMS ungrapple P6 
2000 Dec 4 0030  P6 SAW failed to open latches 
 0100  Noriega ingress 
 0115  Noriega egress 
 0123  2B (+X, stbd) array deploy 
 0137  Noriega ingress 
 0138  2B fully deployed 
 0201  TC closed 
 0202  HC 
 0208:04  Repress (MR) 
 0209  Repress 
 0414  deploy PVR P6 on +Y side of IEA 
 0421  PVR P6 deploy complete 
2000 Dec 5  0052 4B (-X, port) array deploy  
 0246  4B fully deployed 
 1718:25 Depress for EVA-2  92.07 372 x 379 x 51.6 
 1719  Hatch open 
 1721  Battery power 
 1727  Noriega egress (SAFER 7) 
 1734  Tanner egress (SAFER 5) 
 1740  Working at Z1 
 1825  SASA removed from Z1 
 1845  Relocated SASA to P6 
  Wire up P6 
 2030  Prep PMA-2 for move 
 2200  Release straps on aft TCS 
 2340  Tanner ingress 
 2347  Noriega ingress 
 2347  TC closed 
 2354  HC 
 2358:07  Repress; official 6:37:19 
  Deploy aft TCS radiator 
2000 Dec 7   EVA-3 Tanner, Noriega 
 1559  Begin depress  92.05 369 x 380 x 51.6  
 1602  Leak check 
 1604  Resume depress 
 1608:46  Depress (MR) 
 1610  HO 
 1613  Battery 
 1620? Egress 
 1800?  Retension SAWs 
 1815? Install FPP antenna on Unity 
 1955?  Install FPPE on P6 
 2110? Ingress 
 2119  Hatch closed 
 2122:02  Repress 5:14 d; 5:10 NASA 
2000 Dec 8  1436  HO to ISS 
2000 Dec 9  1551  HC to ISS  92.02 368 x 378 x 51.6 
 1913:00  Undock from PMA-3 
 1931  Begin flyaround at 120m 
 2017  Complete flyaround, at 300 m 
 2017  Sep burn 
 2026  Range 500m  91.99 365 x 378 x 51.6 
2000 Dec 10 0139:56  OMS 7 12s 6.5m/s 
 0140:09  OMS 7 CO 
2000 Dec 11 1916:08  PLBD closed  91.71 351 x 365 x 51.6  
 2157:31  OMS DO 2:42 95m/s at apogee 
 2200:12  OMS DO cutoff  88.41 27 x 365 x 51.6  
 2232:02  Entry interface 120 km 
 2303:23  MGTD RW15 KSC 
 2303:35  NGTD 
 2304:20  WS 
2000 Dec 12  0345Tow to OPF/2 