2000-078A
The STS-97 flight took the P6 truss to the International Space Station. The P6 truss was easily latched to Z1 as EVA astronauts Tanner and Noriega guided it in, but during deploy of the solar arrays, a software problem delayed the effort. Solar wing 2B (the starboard wing) and 4B (the port wing) were to be deployed. 2B was deployed and tensioning wires came loose, so the port wing deploy was delayed and done slowly the next day.
On the second EVA P6 was wired up to the station. It was decided to add a new task to EVA-3: repairing 2B's tensioning wires. This was done quickly, and the original taks of installing the Floating Potential Probe experiment was done. This measures whether the PCU's are successful in bleeding off excess charge from the arrays; there was some fear that EVA astronauts might be hit by a bolt of lightning from the arrays. The FPPE was installed on top of P6 between the SAWs. The thermal cover of the FPPE has an evergreen drawn on it as a nod to the tradition of topping out a tall terrestrial construction project.
STS-97 uses RMS 303. Launch mass 120740 kg; landing mass 89756 kg. Mass at MECO 116264 kg, after OMS-2 114777 kg. A new GPS SIGI DTO experiment was carried. 641 kg of internal transfer, possibly including the 40 kg FPPE (of which 23 kg was the actual removable experiment).
| STS-97 | |||
| Date | Time | Event | Orbit |
|---|---|---|---|
| 2000 Oct | Tow to VAB/1 | ||
| 2000 Oct 27 | Mate to ET | ||
| 2000 Oct 31 | Roll to LC39B | ||
| 2000 Dec 1 | 0306:01 | Launch | KSC LC39B |
| 0308:04 | SRB sep | ||
| 0308:15 | OMS assist | ||
| 0309:57 | OMS assist C/O | ||
| 0314:27 | MECO | 74 x 325 km | |
| 0314:46 | ET sep | ||
| 0349:15 | T+0:44 OMS-2 1:18 36m/s | ||
| 0350:34 | OMS-2 CO | 205 x 322 km x 51.6 | |
| 0430? | ET-105 reentry | ||
| 0436:38 | PLBD open | ||
| 0649:17 | OMS 3(R) 10.6s 3m/s | ||
| 0704 | 89.79 205 x 322 x 51.6 | ||
| 1842:39 | RCS NPC +X 20s 1.2m/s | ||
| 2000 Dec 1 | 2021 | RMS checkout | |
| 2130 | RMS cradle | ||
| 2000 Dec 2 | 0323:45 | OMS 4 NC3 52s 24m/s | |
| 0324:37 | OMS 4 CO | ||
| 0600 | 90.66 238 x 374 x 51.6 | ||
| 1600:09 | OMS 5 burn 1:20 dv=38m/s | ||
| 1635:01 | NCC 4s 0.3m/s | ||
| 1732:44 | OMS 6(L) TI burn, range 15 km 2m/s 8s | ||
| 1732:52 | OMS 6 CO | ||
| 1752:43 | MC1 | ||
| 1754 | Station orient, PMA-3 to nadir | ||
| 1812:52 | RCS planar null | ||
| 1829:36 | MC2 | ||
| 1846:36 | MC3 | ||
| 1856:36 | MC4 7s | ||
| 1859 | Manual control 2 km | ||
| 1908 | On R-bar | ||
| 1913 | 150m range | ||
| 1917 | Rotate to align | ||
| 1922 | 100m range | ||
| 1924 | 85m range | ||
| 1927 | 70m | ||
| 1952 | Resume approach at 30m | ||
| 1959:40 | Docking PMA-3 | 92.09 374 x 379 x 51.6 | |
| 2011:51 | Hard dock | ||
| RMS uncradle | |||
| 2216:57 | RMS grapple P6 | ||
| 2227 | P6 unlatched | ||
| 2229 | P6 unberthed | ||
| 2252 | HO to PMA-3 | ||
| 2320 | P6 in park position | ||
| 2000 Dec 3 | 0022 | Ingress to PMA-3 | |
| 0140 | HC to PMA-3 | ||
| 1545 | P6 moving toward Z1 | ||
| 1614 | P6 in premate position 1m from Z1 | ||
| 1820 | Begin depress | ||
| 1823 | 5psi, begin leak check | ||
| 1825 | Resume depress | ||
| 1831 | EVA-1 Tanner, Noriega | ||
| 1830:47 | Depress complete | ||
| 1831 | EAL HO | 92.07 374 x 378 x 51.6 | |
| 1835 | Battery power | ||
| 1840 | Egress Tanner | ||
| 1845? | Egress Noriega | ||
| 1920 | EVA crew observe P6 mating | ||
| 1932 | P6 berthed on Z1 | ||
| 1940? | P6 manually latched | ||
| 2017:25 | RMS ungrapple P6 | ||
| 2000 Dec 4 | 0030 | P6 SAW failed to open latches | |
| 0100 | Noriega ingress | ||
| 0115 | Noriega egress | ||
| 0123 | 2B (+X, stbd) array deploy | ||
| 0137 | Noriega ingress | ||
| 0138 | 2B fully deployed | ||
| 0201 | TC closed | ||
| 0202 | HC | ||
| 0208:04 | Repress (MR) | ||
| 0209 | Repress | ||
| 0414 | deploy PVR P6 on +Y side of IEA | ||
| 0421 | PVR P6 deploy complete | ||
| 2000 Dec 5 | 0052 | 4B (-X, port) array deploy | |
| 0246 | 4B fully deployed | ||
| 1718:25 | Depress for EVA-2 | 92.07 372 x 379 x 51.6 | |
| 1719 | Hatch open | ||
| 1721 | Battery power | ||
| 1727 | Noriega egress (SAFER 7) | ||
| 1734 | Tanner egress (SAFER 5) | ||
| 1740 | Working at Z1 | ||
| 1825 | SASA removed from Z1 | ||
| 1845 | Relocated SASA to P6 | ||
| Wire up P6 | |||
| 2030 | Prep PMA-2 for move | ||
| 2200 | Release straps on aft TCS | ||
| 2340 | Tanner ingress | ||
| 2347 | Noriega ingress | ||
| 2347 | TC closed | ||
| 2354 | HC | ||
| 2358:07 | Repress; official 6:37:19 | ||
| Deploy aft TCS radiator | |||
| 2000 Dec 7 | EVA-3 Tanner, Noriega | ||
| 1559 | Begin depress | 92.05 369 x 380 x 51.6 | |
| 1602 | Leak check | ||
| 1604 | Resume depress | ||
| 1608:46 | Depress (MR) | ||
| 1610 | HO | ||
| 1613 | Battery | ||
| 1620? | Egress | ||
| 1800? | Retension SAWs | ||
| 1815? | Install FPP antenna on Unity | ||
| 1955? | Install FPPE on P6 | ||
| 2110? | Ingress | ||
| 2119 | Hatch closed | ||
| 2122:02 | Repress 5:14 d; 5:10 NASA | ||
| 2000 Dec 8 | 1436 | HO to ISS | |
| 2000 Dec 9 | 1551 | HC to ISS | 92.02 368 x 378 x 51.6 |
| 1913:00 | Undock from PMA-3 | ||
| 1931 | Begin flyaround at 120m | ||
| 2017 | Complete flyaround, at 300 m | ||
| 2017 | Sep burn | ||
| 2026 | Range 500m | 91.99 365 x 378 x 51.6 | |
| 2000 Dec 10 | 0139:56 | OMS 7 12s 6.5m/s | |
| 0140:09 | OMS 7 CO | ||
| 2000 Dec 11 | 1916:08 | PLBD closed | 91.71 351 x 365 x 51.6 |
| 2157:31 | OMS DO 2:42 95m/s at apogee | ||
| 2200:12 | OMS DO cutoff | 88.41 27 x 365 x 51.6 | |
| 2232:02 | Entry interface 120 km | ||
| 2303:23 | MGTD RW15 KSC | ||
| 2303:35 | NGTD | ||
| 2304:20 | WS | ||
| 2000 Dec 12 | 0345 | Tow to OPF/2 | |