Friday, May 4, 2007

DART

 2005-014A


48 kg NASA/Orbital experiment, Demonstration of Autonomous Rendezvous Technology. Mass 350 kg, size 1.8m long 1.0m dia. The DART AVGS payload is attached to the HAPS fourth stage of the Pegasus launch vehicle and has propulsion, AVGS, RCS, batteries, and communications. DART is an MSFC project which grew out of the VGS experiment on the Spartan-201 satellite carried on STS-87 and STS-95.

HAPS capacity is 57 kg prop and has three 220N thrusters. The AVGS bus has 16 cold-gas 3.5N, Isp=60s N2 thrusters with 23 kg prop capacity. It is 0.6m dia 0.6m long (0.9m long with GPS antenna etc) while HAPS is 1.0m dia 1.0m long.

Rendezvous with MUBLCOM at 150m R-bar stationkeep. The entire mission is preprogrammed, without ground command during flight. The misson was monitored at VAFB's DART Mission Ops Center. After reaching 95m to MUBLCOM, DART detected that it was unexpectedly low on fuel and moved away to abort the mission. Post-flight analysis revealed that DART had collided with MUBLCOM due to multiple software and algorithmic problems.

The TLEs for DART show it in the MUBLCOM orbit until Apr 18; no TLEs for MUBLCOM exist for Apr 16-18. OSC reports the DART safing burn was on Apr 16; I conclude that the DART TLEs for Apr 17-18 actually belong to MUBLCOM.


DART 
 

DateTimeEventOrbit  

2005 Apr 15  1627  L-1011 T/O from VAFB 
 1726:50 Drop 
 1726:55  T+0:05 S1 burn 11.5 km 0.442 km/s 
 1728 T+1:17 S1 off 63.1 km 1.606 km/s 
 1728  T+1:35 S2 on 88.0 km 2.429 km/s 
 1728  T+1:50 Fairing 108.6 km 2.710 km/s 
 1729  T+2:48 S2 off 216.1 km 5.428 km/s 
 1735:21? Stage 2 sep 
 1735:30  T+8:40 S3 on  
 1736:35? T+9:45? S3 off 7.545 km/s 0.0 deg  400 x 547 x 97.7  
  On orbit checkout in phasing orbit 1 
 1738:41? S3 sep 
 1738:45? HAPS burn 1  
 1739:20? HAPS cutoff  500 x 756 x 97.7  
  Phasing orbit 2  
2005 Apr 16  HAPS burn 2 
 0055? T+7:29:00 HAPS burn 2 cutoff  739 x 742 x 97.7  
  T+7:29:00 DART 40 km behind and 7.5 km below MUBLCOM  
  T+7:55:42 DART CW Transfer burn 1A?, to range 3 km 
  T+8:36:49 DART stationkeep at 3 km 
  T+8:51:49 DART CW transfer burn 2A?, to range 1 km  
  T+10:08:05 DART stationkeep at 1 km 
 0340? T+10:13:05 Approach to 95m  740 x 746 x 97.7 
  X-1:23 Collision avoidance activated 
 0418:46  X+0:00 Impact MUBLCOM 
  T+11hr, X+0:03:49 Retreat to 300m 
 1047   740 x 751 x 97.7 
2005 Apr 16  1715:45  Retirement burn  
 1724:11  Safed 
 1753:09  Transmitter on to deplete battery 
2005 Apr 18   394 x 746 x 97.7 


Planned DART proxops 
 

DateTimeEventOrbit  

  T+11:10:34 -Vbar rendezvous at 15m 
  T+12:59:20 Stationkeep at 15m on target docking axis 
  T+13:06:31 Approaches to 5m with avoidance tests 
  T+13:43:12 Retreat to -100m on Vbar  
  T+14:21:35 Simulated avoidance 
  T+14:29:53 Retreat to -200m on -Vbar 
  T+15:23:48 Flyaround to +Rbar (nadir) at 150m 
  +Rbar approach to 100m 
  +Rbar retreat to 300m 
  Flyaround to +Vbar, -Rbar, -Vbar 
  Second -Vbar approach to 200m 
  Flyaround to +Rbar, rerendezvous 
  T+19:59:23 Second +Rbar approach to 100m 
  Retreat to 300m 
  T+20:22:26 HAPS Retirement burn, lower perigee 