2017-005A
Launch of DSN 1 was delayed due to a construction accident. For DSN 2 the MELCO DS-2000 bus was used but NEC was given the contract for system integration.
| DSN2 | |||
| Date | Time | Event | Orbit |
|---|---|---|---|
| 2017 Jan 24 | 0744:00 | Launch by H2A-32 | |
| T+1:56 SRB burnout, 68 km | |||
| T+2:07 SRB 1-2 sep, 79 km | |||
| T+2:10 SRB 3-4 sep, 83 km | |||
| T+3:25 Fairing sep, 150 km | |||
| 0750 | T+6:40 MECO, 242 km, 6.1 km/s | ||
| T+6:48 Stage 1 sep, 245 km, 6.1 km/s | |||
| T+6:54 SEIG-1, 247 km, 6.1 km/s | |||
| 0755 | T+11:07 SECO-1 262 km, 7.7 km/s | ||
| 0806 | T+22:46 SEIG-2, 189 km, 7.8 km/s | ||
| 0810 | T+26:37 SECO-2 197 km 10.2 km/s | ||
| 0818 | Stage 2 sep | 190 x 35000? x 19? | |