Sunday, March 11, 2018

STS-123 (Endeavour)

 2008-009A


122364 kg launch, 94157 kg landing.

EMU 3004 (Linnehan) and 3003 (Foreman, Behnken) will be left on ISS, and EMU 3006 and 3008 will be returned.

EVA1: EV4 Reisman 3006, EV1 Linnehan 3004

Prep JLP for unberth, install OTCM on SPDM and prep SPDM. JEM ELM-PS to Node 2 zenith.

EVA2: EV1 Linnehan 3004, EV3 Foreman 3003

Deploy SPDM in bay.

EVA3: EV2 Behnken 3008, EV1 Linnehan 3004

Install OTP and THA on SPDM, install CLPA, transfer LWAPA to COL-EPF, install MISSE 6, transfer Yaw Joint and DCSU 1/2 to ESP-2.

LWAPA goes on the nadir EPF (SDN) and MISSE 6 PEC 6a/6b are attached to it.

EVA4: Foreman 3008, Behnken 3003

S0 RPCM repair, Z1 reconfig, T-RAD DTO.

EVA5: Foreman 3008, Behnken 3003

Install OBSS KAU; OBSS transfer to S1, SARJ TBA-5 install

Contingency: Linnehan 3006, Foreman 3008

Total cargo up 17048 kg. Cargo left in space: Dextre, ELM-PS, 3 ORUs, and 2 MISSE PEC for a total of 10974 kg; MISSE LWAPA and OBSS puts it up to 11456 kg, so cargo down 5592.

Cargo STS to ISS outside: 10785 kg including 8336 kg ELM and 1556 kg Dextre, 893 kg other (not including OBSS?) inside: 650 kg plus 286 kg consumables. ISS to MD, 710 kg. MD cargo includes two EMU up and down and a 5 kg RPCM down.


STS-123 
 

DateTimeEventOrbit  

2007 Aug   Begin processing in OPF/2 
2008 Feb 11   Tow to VAB 
2008 Mar 11  0628:14  Launch  
 0630:18 SRB sep 
 0630:29  OMS ASS 
 0632:23  OMS ASS CO 
 0636:37  MECO  87.34 56 x 229 x 51.6  
 0636:59  ET sep 
 0706:44 OMS-2 
 0707:47  OMS-2 CO 
 0823:02 PLBD open  89.16 177 x 288 x 51.6  
 0937:37  OMS-3 NC1 burn  89.17 179 x 287 x 51.6  
 0938:26  OMS-3 CO 
 2334:44  OMS-4 R  
 2335:01  OMS-4 CO 
2008 Mar 12    89.28 190 x 287 x 51.6  
 2211:09  OMS-5 NH burn  89.29 193 x 284 x 51.6  
 2212:05  OMS-5 CO 
 2310:32 NC4 OMS-6 both, 112693 kg 
 2311:31  OMS-6 CO 
 2347?  NCC 
2008 Mar 13  
 0042:22 TI OMS-7 L 111642 kg 2.8 m/s 
 0042:33  OMS-7 CO 
 0105  MC1 
  MC2 
 0154  MC3 
 0204  MC4, 520m  
 0220  200m below station 
 0235  RPM complete 
 0240  Begin flyaround from +Rbar to Vbar 
 0258  On +Vbar at 114m 
 0300  Begin approach on Vbar 
 0315  60m 
 0325  40m 
 0337  20m 
 0349:48 Docking  91.35 339 x 341 x 51.6  
 0537  HO 
 0700? SSRMS grapple SLP 
 0730?  SLP unberthed  91.35 339 x 341 x 51.6 
 0746  SLP in motion 
 0750  Reisman seat liner on Soyuz; crew swap 
 0800? SLP berthed on truss POA on MBS 
 0820? SSRMS ungrapple SLP 
2008 Mar 14  
  EVA-1 Reisman, Linnehan 
 0100  Begin depress  
 0104  2.0 psi 
 0108  Pressure 1 psi 
 0113  0.7 psi  
 0118  HO 
 0118  Battery power 
 0126  Egress Linnehan 
 0144  Egress Reisman 
 0300  Complete JLP prep 
 0322  SRMS grapple JLP 
 0400  Working on SLP 
 0506  OCTM-2 attached to Dextre 
 0632  JLP latches open 
 0634  JLP unberthed by RMS 
 0747? Ingress Reisman 
 0801  Ingress Linnehan 
 0802?  TC 
 0804  JLP RTL on Node 2 
 0806  JLP berthed on Harmony zenith 
 0814  HC  
 0819  Repress 
 2257  JLP power OK 
 2349  SSRMS grapple OBSS 
2008 Mar 15  0013  OBSS grapple by SRMS 
 0038 OBSS ungrapple by SSRMS 
 0125  HO to JLP, ingress 
 0202  SSRMS grapple SPDM  91.35 339 x 341 x 51.6  
 0210  SPDM has power 

  
  EVA-2 Linnehan, Foreman 
 2343  Depress 0.7 
 2348? HO 
 2349 BP 
2008 Mar 16  0000?  Egress Linnehan 
 0005  Egress Foreman 
 0230? Arm 1 unberthed 
 0255  Arm 1 on temp SLP stow 
 0353  Arm 2 unberthed 
 0450  Arm 2 on SPDM 
 0500  Arm 1 off temp stwow 
 0510  Arm 2 on SPDM 
  SPDM assembly 
 0610  Foreman returning to Quest 
 0621 Foreman ingress? 
 0631  Linnehan to CETA cart to stow APFR 
 0638  Foreman inside airlock 
 0647  Linnehan ingress 
 0647  TC closed 
 0654  HC 
 0657  Repress 
 s  SSRMS grapple SPDM 
2008 Mar 17   EVA-3 
 2227  7 psi 
 2231  5 psi, pause 
 2237  2 psi, pause 
 2244  Below 1 psi 
 2246? Depress 
 2248  0.5 psi 
 2251  HO 
 2251  Battery power 
 2300? Behnken egress 
 2305 Linnehan egress 
 2348  Working on SLP at MBS 
2008 Mar 18 
 0040? OTP unberth 
 0116  Completed OTP SPDM tool platform install  
 0154  Linnehan retrieving LWAPA 
 0159  LWAPA unberthed 
 0206  Carrying LWAPA to COL EPF  91.35 340 x 341 x 51.6  
 0222  LWAPA installed on COL EPF 
 0240  Linnehan at Yaw Joint  
 0246  YJ unberthed  
 0304 YJ on esp2 
 0313 Linnehan leaving esp2 
 0330 Linnehan unberthed dcsu 
 0340? MISSE 6bunberthed by Behnken 
 0350? DCSU at ESP2 
 0354 MISSE PEC 6b near LWAPA by Behnken 
  Problems installing PEC 
 0412  DCSU-2 unberthed by Linnenhan 
 0423  Abandon attempts to install PEC 
 0450? MISSE PEC returned to PLB 
 0508  Cleanup 
 0527  Linnehan ingress 
 0536  Behnken ingress 
 0541  HC 
 0545  Repress (NASA 6:53) 
 0615?  SSRMS grapple SPDM 
 0730?  SPDM on SSRMS out of SLP 
 1955  SPDM grapple contact with Destiny 
 2000  SPDM grappled PDGF on Destiny 
 2124  SPDM based on Destiny 
2008 Mar 19  0140  SSRMS ungrapple SPDM 
 0220  SSRMS grapple SLP 
 0240? SLP unberthed from P1 POA 
 0352  SLP keel latch in PLB 
 0354  SLP berthed 
 0402  SSRMS ungrapple SLP 
2008 Mar 20  2135  Depress underway 
  EVA-4 Foreman, Behnken 
 2156  1.0 psi 
 2159  Depress 
 2200  0.6 psi 
 2203  Go for HO 
 2203  HO? 
 2204  Battery power 
 2211  Egress Behnken 
 2222  Egress Foreman 
 2245  broken RPCM removed from S0 truss 
 2300  Failed to fix connector on Z1 
 2320  Prep for T-RAD DTO 
2008 Mar 21  
 0200  T-RAD complete 
 0245  Stowing T-RAD eqpt 
 0414  Ingress Foreman 
 0417  Ingress Behnken 
 0418  TC closed 
 0425  HC 
 0428  Repress 
 
  Transfer Expr3 from Destiny to Col 
 2000? OBSS on SRMS for survey 
2008 Mar 22  
  EVA-5 Foreman, Behnken  
 2024  2 psi  
 2028  1 psi  
 2029  0.8 psi  
 2030  DEPRESS 
 2030  0.6 psi  
 2032  0.5 psi  
 2034  HO  
 2034  BP  
 2040  Foreman egress 
 2046  Go to grapple OBSS 
 2047  Behnken egress 
 2051  Grapple OBSS with SSRMS 
 2102  SRMS ungrapple OBSS 
 2125  Avionics box installed on truss 
 2220  OBSS nearly on truss 
 2232  SSRMS ungrapple OBSS, in EV hands 
 2241  OBSS soft docked to S1 truss 
 2330  SARJ inspection 
 2339? MISSE PEC unberthed  
2008 Mar 23  0000?  MISSE PEC6a installed?  91.35 340 x 341 x 51.6  
 0010? MISSE PEC unberthed 
 0027  MISSE PEC installed on LWAPA 
 0145  Thermal covers on JLP trunnions 
 0145  SARJ inspection complete 
 0221  ingress 
 0226 ingress complete 
 0227  tc 
 0231  HC 
 0236 Repress 
2008 Mar 24  
 2149  HC to ISS 
2008 Mar 25 
 0025:01  Undocking  
 0043 250 ft 
 0044 347 ft 
 0048 425 ft 
 0052 begin flyaround 
 0102 zenith 
 0115 behind 
 0123 nadir 
 0136 sep1 
 0204  sep2  91.36 340 x 342 x 51.6  
 1753s  OMS adjust  91.41 341 x 346 x 51.6  
2008 Mar 26 
 1923:49  PLBD closed  91.41 341 x 346 x 51.6  
 2333:14 OMS DO 2:45 92.0m/s  42 x 352  
 2335:59  OMS DO CO 
2008 Mar 27  0007:29  EI 
 0039:08  15:18:10:54 MGTD KSC RW15 
 0039:17 NGTD  
 0040:41  WS 